We have the option to close a purchase order automatically set to when the balance is zero. Is there a way to close a purchase order during accounts payable entry when the invoice is less than the total purchase order?
What's the best way to apply a paid invoice to an open Purchase Order?
Purchase Order Created.
Invoice Entered; not applied to PO.
No notification from Sage that there are open purchase orders for that job with this vendor.
Invoice Paid.
Period…
Hi,
I have a two part question.
1. I noticed that when I enter a PO, assign it to a project and the relevant cost code etc. it does not hit my committed cost. How do I get that PO cost committed?
2. If I get a Prime change approved, then write…