Please note:
In V11.0.7 when a work order components are partially tracked the start and end dates fields get cleared on the GESMFG screen.
Steps to replicate:
- GESBODP (BOMS): select an existing production BOM INT501 site NA023 (SEED Folder).
- GESMFG (work order): generate a work order for the above BOM.
- Scheduling mode – Forward
- Start date – 04/05/18
- End date – 04/05/18
- Allocation – Complete
- Scheduling – Scheduled
- GESMTK (production tracking): Create a partial material tracking for the above WO.
- GESMFG (work order): Start date and end date is cleared out from the work order
Issue is fixed in request # 85637
- Maintenance # 3401 - V11.0.9
- Maintenance# 3279 - PU9
Please test the fixes prior to applying it in your PROD folder.
Note: TEST folder has to be set to TEST and SPECIF prior to applying the hot fixes.
You can verify this in GMAINT table name ADOVAL and field name VALEUR = 2 .
Use the following selection criteria
PARAM = "TEST"
&
PARAM = "SPECIF"
- If your folder is at V11 patch 7 there are no dependencies. Only apply hot fix 3401.
- If your folder is at PU9 patch 7 there are two dependencies, hot fixes 3279 and 3050 (request# 68811).