Having issues since estimating upgrade to SQL 17.13 unable to interface with Job Cost on our accounting system which is still Pervasive

SUGGESTED

Since Estimating side has been upgraded to SQL V 17.13 unable to interface with Pervasive version of accounting unable to import into the Job Cost side, rejects all items saying the unit descriptions don't match, but the import Settings on the Job Cost side the "Override CUD" is not checked" Has anyone else seen this ?

Parents
  • 0
    SUGGESTED

    Does the error message say "units" don't match or "Descriptions" don't match? If it's "Units", I found this in the KB: 

    You must change the units to match and be the same in both applications, either in Estimating or in Job Cost.

    New Jobs:

    1. In Job Cost go to Setup, Standard Cost Code.

    2. Select the affected cost code.

    3. Modify the cost code to match the item on the Estimate in Estimating or remove the Unit of Measure from the Standard cost code.

    Jobs that are fully set up or in progress:

    1. In Job Cost go to Set up, Category.

    Note: If you do not use Categories go to Set Up, Cost Code.

    2. Select the affected Category.

    3. Modify the Unit Description on the Category to match item on the Estimate in Estimating.

     
    AND THE BELOW MIGHT BE YOUR BEST CHOICE:

    If you only care about the Amounts and not the unit of measures:

    1. In Job Cost select File, Compnay Settings, JC Settings, Import
    2. Un-Check Reject if different Cost Unit Description
    3. Select OK

      Please let me know what you end up doing. Thanks!
  • 0 in reply to twse

    TWSE,

    We have verified each item on the estimate before trying to interface, the rejection settings in job cost are not checked. The error messages vary. But it short, it is rejecting every item in the estimate, and you can go through and change each item and try again, and it will reject every item that you have changed. I have a view set-up on the spread sheet that I can view every Job Cost Code and Category  for every item, and they all match Job Cost Phases and Categories. Any other things that I might try?

    Thanks,

    Bill

  • 0 in reply to Bill L

    So in this scenario, I'd start in "the shallow end of the pool" 1st. What I mean is make a "new" estimate (don't copy an old one) and take off only ONE item. Do NOT change the item's description, cost codes, etc.  BUT before you make this New estimate with only ONE item, refresh the company folder (Database>Settings> refresh). This will pull in the most current Job Cost info into the Estimating DB JC/AB list features

    Try to send that test estimate to a dummy job in job cost. The idea being that we need to test the most simplest scenario and if that works, that tells us something, if it doesn't work that also tells us something.

    IF it doesn't work, use the list button on your Spreadsheet Layout to pick from that list the cost code and the cost category from the actual list of codes in Job Cost. Then try to send to JC again.

    If it does work, well now you just need to drill down into that one item to see what's different on it as compared to the real estimate you're working on. I'd recommend using the Detail Window for drilling down in this scenario.

    Please let me know how it goes, thanks!

Reply
  • 0 in reply to Bill L

    So in this scenario, I'd start in "the shallow end of the pool" 1st. What I mean is make a "new" estimate (don't copy an old one) and take off only ONE item. Do NOT change the item's description, cost codes, etc.  BUT before you make this New estimate with only ONE item, refresh the company folder (Database>Settings> refresh). This will pull in the most current Job Cost info into the Estimating DB JC/AB list features

    Try to send that test estimate to a dummy job in job cost. The idea being that we need to test the most simplest scenario and if that works, that tells us something, if it doesn't work that also tells us something.

    IF it doesn't work, use the list button on your Spreadsheet Layout to pick from that list the cost code and the cost category from the actual list of codes in Job Cost. Then try to send to JC again.

    If it does work, well now you just need to drill down into that one item to see what's different on it as compared to the real estimate you're working on. I'd recommend using the Detail Window for drilling down in this scenario.

    Please let me know how it goes, thanks!