What is the proper way to change a cost code from the original estimate? The original estimate was entered thru JC - Tasks - enter Estimates, as one amount now the PM wants to break out that one amount into multiple cost codes.
What is the proper way to change a cost code from the original estimate? The original estimate was entered thru JC - Tasks - enter Estimates, as one amount now the PM wants to break out that one amount into multiple cost codes.
You can go to JC > Tasks > Enter Estimates and using the original date of the prior entry, enter a negative amount to the existing cost code and enter positive amounts to the desire re-allocation of the estimate.
Art MInds
Senior Independent Consultant
You can go to JC > Tasks > Enter Estimates and using the original date of the prior entry, enter a negative amount to the existing cost code and enter positive amounts to the desire re-allocation of the estimate.
Art MInds
Senior Independent Consultant