300 CRE Server Upgrade/Migration.

We need to upgrade from 300 CRE 15.1 to 16.1.
Also need to upgrade from old server 2008 r2 to new server 2012 r2.

Will need to do it over a weekend, so I'd like to get the road mapped out as Specifically as possible.

Which is recommended?

1. - Upgrade current Server2008 15.1 to 16.1 them migrate to new Server2012
2. - Migrate 2008 15.1 to new 2012 machine then upgrade to 16.1
3. - Build new Server 2012, install clean 16.1, copy 15.1 data, upgrade files, crystal reports, etc.

I like the 3rd option, but just want to make sure I'm not missing a step that would rule it out.  Once the old server is powered down, and all local DHCP/DNS records removed, never rebooting it would be perfect.

Because of the images in the TimberScan database, I plan to keep the "\\server-name" the same.

Also - I'm using Storage Craft Shadow Protect, so I'll have mountable images of the drives I can drag and drop the old server's data from at any time.

Any and all help is appreciated.  As many specifics as possible because I won't be able to call sage support on the weekend.

Thanks,

    Chad

  • 0
    Hi Chad,

    #3 should be fine. I would also recommend using the Sage migration tool as it will bring over all security, report menu customizations, attachments, etc., in addition to the data.

    You should make sure all your custom reports are in the same location.

    With TimberScan, you can find/replace the server name within the SQL database. You should also consider engaging Core Associates to ensure the transition is smooth for TimberScan.

    If you need any help, feel free to contact me.

    Thanks!

    John DiCostanzo
    Managing Partner | Nexus Consulting