Hello John,
The JC Profit, JC Profit (as of Date), JC Profit Variance, JC Work in Progress report report all use the % Complete entered for the Job.
Knowledgebase article 45287 has attached a PJ Schedule of Work in Progress that also uses the % Complete entered for the JC Job.
These reports only capture "entered" percentages for job totals not individual cost code and/or category line items. There is a Labor Hours report PJ-Labor Hours that utilizes the % Complete by Cost Code or Category. What job cost reports will capture these entries by Cost Code?