Adjust cost code from Contingency

How do I move around cost codes internally without affecting the budget or creating an "Approved" change order.   This is an internal adjustment, reducing the contingency amount and re-allocating to cost codes. 

Parents
  • 0

    Create a change order at menu 6-4-1, don't put anything on the Prime details tab, just use the budget details tab.  Enter a credit for the contingency cost code and positive values for whatever codes you want to distribute it to.  I like to create a change order type at the top and call in in-house or budget only.   Something to distinguish between that and regular client change orders.   It does have to be an "approved' status to be reflected on job cost reports.

Reply
  • 0

    Create a change order at menu 6-4-1, don't put anything on the Prime details tab, just use the budget details tab.  Enter a credit for the contingency cost code and positive values for whatever codes you want to distribute it to.  I like to create a change order type at the top and call in in-house or budget only.   Something to distinguish between that and regular client change orders.   It does have to be an "approved' status to be reflected on job cost reports.

Children
No Data