PO blanket orders with MRP

  • Is there a way you can use a blanket or Master order and have MRP read the projections on the order?  Has anyone written an enhancement for this?

  • I do not know if this problem with sage ERP like?But there is a fundamental problem in management.
    We can program and run reports to analyze or synthesize to get your requirements a flexible way that is not a highly technical matters

  • If it's a blanket order, are you using different Required Dates on each line?  MRP should read those required dates.